The school’s extension is soon to be completed but there is still a long way to go.
The project at St Joseph’s School is a large classroom extension, on a programme of 20 weeks which started in October 2018. As we are main contractor for this site, we have worked from the ground up, however before drainage works could go ahead there was a set back after the soil sample was taken, which set the programme back by 4 weeks. Once everything was made good the work was able to go ahead. In the next couple of months, the following internal works are left to be completed; suspended ceiling, electrical, plumbing, plastering, carpentry, flooring and decoration.