Project Description

After being instructed by CP Associates, works had taken place to create a single storey classroom extension to form 2 new classrooms. Works included all building control, groundworks, build, internal finishes, LED upgrade to new and existing classroom together, along with decoration. Works was undertaken from the first week in September 2018 until the end of March 2019. The project originally had a programme of 16 weeks but was put back weeks due to soil samples needing to be evaluated and many variations. Total cost came to a total of £240k. Below some before and after pictures.