Dig Street Project

Project Description
This first floor flat in the heart of Ashbourne Derbyshire was in dire need of an upgrade, on behalf of ‘Derbyshire Building Trust’ we were the chosen contractors to carry out the works. This was a tightly budgeted project with available funds of £25,000.00 +VAT to upgrade the accommodation to a modern, eco-friendly apartment in line with current building legislations. The works involved a new bathroom and kitchen installation with complete electrical and plumbing re-fit. The job was completed on time (a tight 2 month programme of works) and within budget – we even managed to value engineer savings of £4,500.00 +VAT to the client!.